Progress in Phase 1

  • During the summer of 2020, the following items are underway in Phase 1 of the district's six-phase capital improvement project:

    Roof work at Allendale Elementary, West Elementary and West Middle schools

    Masonry work, including repointing and repairs, at West Senior, East Senior and West Middle schools

    Turf field and road replacement at East Senior High School
    Watch a time lapse video of the paving of track loop binder course from Young and Wright Architectural.

    Drinking fountains at West Middle School

     

    Next up:

    Turf field at West Senior High School

     

  • Updates on
    Capital Project
     

    View the update presented Oct. 29, 2019 at the Board of Education Meeting.

    View the update presented Aug. 5, 2019 at the Board of Education Meeting.